This project consisted of a timber structure building with multiple addons through the years. Once an extended bar area of the pub it now had to be removed to make way for a new through road for 4 new house built at the rear.
SO Demolition provided site segregation, all plant and machinery. We soft stripped the area then carefully completed the cut away from the retaining building. The structure was very close to the new houses that had been built so extreme care had to be taken.
Once dismantled the larger beams were set aside for the client’s reuse. All other arisings were removed from site to licenced waste facilities. Ground slab and footings removed and site left ready for following on trades.
This project took a total of 3 days from set up to completion.