SO Demolition carried out the careful soft strip first on this wonderful mansion house in St. Johns Wood, London.
All Internal fixtures and fitting, coverings and decorative timber work was removed via wait a load trucks and compound space was limited for skips. All M+E services were isolated by the client on this project and certified. Extra careful attention had to be taken about the existing windows and staircase.
The Phase one demolition followed on from the soft strip and comprised of removing all the existing lav & plaster from every part of the house. This was so the structural engineer could determine which wall were non-bearing. Once clear marked these timber non-load bearing wall were removed and all remaining timber joists de-nails to leave a clean flush finish to receive a new covering.