SO Demolition completed a full start to finish on this project within 2 weeks. R&D asbestos survey arranged and completed in the first week as well as utility isolation, temporary water install for dust suppression and site set up. The second week began with the strip out of the house and completing the demolition with all waste cleared from site.
The client Demolished the property to create space for an extended car fore court for the car sales show room next door. The house footprint left a 150mm recess so SO Demolition was contracted to create a level area using reinforcement mesh and concrete and a ramp at the rear of the property.
The Client was extremely happy with the finished product and the quick turn around from start to finish.